The Contributors:
Association of General Contractors Project Coordination
CAD of Puget Sound CAD Service
Cadman Sand and Gravel 50 Tons of CSBC
Cascade Door & Hardware Mechanical Room Doors/Frame/Hardware
Cascade Saw & Drill LF Sawcut
CEMEX All Concrete & Aggregates
Central Rebar Rebar Installation
CITC Labor
Comast Cedar Fence/Trail Gravel/Plant Installation
Conco Aggregate Conveyance
Concrete Technology Hollow Core Panels
Emerald City Temporary Fencing
Glacier Sand & Gravel 300 tons CSBC
Granite Northwest Project Management/Labor
Gray & Osborne, Inc Design/Engineering
H.D. Fowler Pipe Material
Hanson Products Pre-cast Manholes
Harmsen & Associates Site Survey
Harris Rebar Rebar (30,000 lbs)
Hertz Rentals Excavation/Grading Equipment
International Belt & Rubber Supplies Neoprene Gaskets
Iron Mountain 90 Ton CSBC
Lease, Crutcher, & Lewis Mechanical Room Landing/Stairs/Rails
Mason Supply Concrete Forms/Scaffold Equipment
Matheus Lumber Co. Concrete Form Lumber
Mc Nichols Products Stainless Steel Water Intake Screen
Menzel Lake Sand & Gravel Stream-bed Gravel
National Waterworks Pipe Material
Nelson Trucking Delivery Trucking & Material Delivery
Northwest Cascade, Inc. Job Site Honey Buckets
NW Erosion Control Erosion/Sediment Control
Rain For Rent Pumps For Pond Draining
Ralphs Concrete Pumping Concrete Pumping Service
Rebar International Install Wall Rebar
Reliable Concrete Pumping Concrete Pumping Service
RG Sales Rubber Liner Leak Repair
Riverside Sand & Gravel Gravel Delivery
Service Electric All Electrical Connections
Spears Manufacturing PVC pipes fittings/Valves
Spring Brook Clearing Debris Disposal
TNEMEC Waterproof Paint for Vault
United Trench Shoring Excavation Trench Box
University Mechanical Mechanical/Plumbing
Vector Industries Stainless Steel Drilling
Ventilation Power Cleaning Vactor Truck
White Cap Forming Materials
Whitney Equipment Water Pumps/Circuit Board
ESTIMATED VALUE OF DONATED EQUIPMENT, MATERIALS, AND LABOR*
$1,500,000
*Estimate based on finished product costs at non-discounted prices;
new partners are being recruited and will add to this value estimate.
CASH DONATIONS THE SITE
Tulalip Tribes Snohomish County’s
$180,000 Mc Collum Park
Larry Torgerson Memorial Fund
$5,000
Adopt-A-Stream Foundation
$15,000
TOTAL
$200,000
THIS HAS BEEN A WONDERFUL VERY SLOW “AMISH BARN BUILDING” EVENT THAT COULD NOT HAVE BEEN ACCOMPLISHED WITHOUT THE GENEROSITY OF EVERYONE ABOVE!!!!
Return to Northwest Stream Center
OR